El lun, 10-07-2017 a las 14:18 -0400, langdon escribió:
As we run up to the F26 release, I know we have a number of things
still
in flight for the modular release of Boltron. As it is non-blocking
to
the release, we won't be holding the release back to make sure
Boltron
goes out, which is fine.
However, I notice that the schedule for the F27 Mass Rebuild is July
12
(the day after tomorrow). I am concerned that if Boltron (or
anything
else slips), everyone will have to prioritize F27 Mass Rebuild vs
F26
final bits & pieces. Would it make sense to consider pushing the
Mass
Rebuild out a week to July 19th? Would there be significant
downstream
(in schedule terms) effect?
Sorry I am catching up from email still from meetings and PTO and just
saw this. We ended up having to slip the mass rebuild due to other
issues and got Boltron out. However I honestly would not hold up
something like the mass rebuild for Boltron as holding up the mass
rebuiold forces a slip in the next fedora release.
Dennis