Thanks to everyone's hard work the current sprint (2012.10.1) is well underway.
Given the unfortunate tendency of time to slip away, you may want to keep the following
dates in mind:
Tue 23-Oct
* All patches to list
Wed 24-Oct
* All commits and pull requests merged to master
Thu 25-Oct
* Integration/burn in time -- dev should be:
* actively engaged with QE efforts to ensure everything works end-to-end and
rectify cases where that is not true
* work to define stories for the next sprint
* freshen up documentation on the wiki/site
Thu 01-Nov
End of Sprint Review and Demos
Note that this leaves less than a week for development of current features. If you have
something that is likely to slip, please raise a red flag early and often. And please keep
an eye on the mailing lists for patches and pull requests in need of love.
I have added these dates to the
aeolusproject.org wiki[1]
Thank you!
Steve Linabery (eggs|eggmaster)
[1]
https://redmine.aeolusproject.org/redmine/projects/aeolus/wiki/2012_10_1_...