Hi John,
(Cc-ing fedora-devel-list, surprised to see the schedule hasn't been posted there)
On Mon, 2009-07-13 at 21:09 -0700, John Poelstra wrote:
http://poelstra.fedorapeople.org/schedules/f-12/f-12-releng-tasks.html http://poelstra.fedorapeople.org/schedules/f-12/f-12-releng.ics
In the F-11 schedule, we had 85 days between Feature Freeze and GA. And then GA slipped by two weeks.
In the F-12 schedule, we now have 99 days between Feature Freeze and GA.
This seriously cuts into development time, and we already have a shorter releases cycle.
Why is that?
Thanks, Mark.